Ethiopia’s GERD dam expected to be completed by 2022 after delays
Officials and hydraulic experts said the $5 billion Nile project was 65% complete, with delays linked to planning and equipment supply.

Ethiopia’s Grand Ethiopian Renaissance Dam (GERD) was expected to be completed by 2022, officials and hydraulic experts said at a panel discussion, after delays to the $5 billion project on the Nile. The forecast was for construction to finish; the discussion did not give a separate date for when the dam would begin operating.
The project was launched in May 2011 to generate 6,000 megawatts of electricity for Ethiopia’s development and to support electricity exports to neighbouring countries. The delay matters to Ethiopia’s plans for domestic power and regional sales, but the announcement did not set out when either would begin.
What caused the delay?
The panel acknowledged that the project began before an in-depth study had been carried out, which contributed to the delay, according to local broadcaster FANA. The Ministry of Water and Energy said the delay had added $800 million to the project’s cost.
Prime Minister Abiy Ahmed blamed the military-based contractor Metal and Engineering Corporation (METEC) for failing to supply electro-mechanical equipment required under its contract. The article also said METEC had faced scrutiny over the handling of public funds, but gave no further detail about the allegations or their outcome.
How much work remained?
The Ministry of Water and Power put construction at 65% complete. It did not provide a revised construction schedule or explain which stages remained before completion. The forecast of a 2022 finish was an expectation expressed at the panel, not confirmation that the dam would be operational by then.
The panel was also discussing public participation, relations between Ethiopia, Sudan and Egypt, and agreements on electricity interconnection and exports. The project was described as financed wholly by Ethiopians through bond purchases. The discussion did not announce any new agreement with the two downstream countries or provide details on future export arrangements.